Description
  • Performed the role of client technical consultant to conduct performance testing and verification consultancy.
  • Evaluation of the Chilled water network of the AC Plants – AC Plant 1, 2, 3, 4, 5, 7, 8, Tower AC plant, EXPEC AC Plant, AL Midra & North Park, ITC AC Plant.
  • Study the compatibility issues on the hot side of the ETS Stations during the changeover to the District Cooling Chilled water network.
  • Hydraulic Evaluation to verify the existing pump capacity & operation.
  • General Observation Of The ETS.
  • Verification of the Heat Exchanger Design Capacity based on NTU Method.
  • Evaluation of the current operation & Control sequence.
  • Report preparation for the validation of the existing system and recommendations to improve the performance.